Stage Time
Critical Initial Planning 3 months
Approval of Outline Business Case 1 month
OJEU Publication and pre-qualification of bidders 3 months
Shortlisting bidders 1 month
Issue ITN and receipt of initial bids 3 months
Evaluation of bids and best and final offers 3 months
Approval of Full Business Case and preferred bidder 1 month
Final negotiations to contract award 3 months