Stages and Timetable of a PPP Project
|
Stage
|
Time
|
|
Critical Initial Planning
|
3 months
|
|
Approval of Outline Business Case
|
1 month
|
|
OJEU Publication and pre-qualification of bidders
|
3 months
|
|
Shortlisting bidders
|
1 month
|
|
Issue ITN and receipt of initial bids
|
3 months
|
|
Evaluation of bids and best and final offers
|
3 months
|
|
Approval of Full Business Case and preferred bidder
|
1 month
|
|
Final negotiations to contract award
|
3 months
|